PMP考试样题

ChinaITLab.com   2003-7-31  保存本文  推荐给好友  QQ上看本站  收藏本站



  1. While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract. You should:
  
  Honor the customer's request as sign of cooperation to ensure future business.
  Refuse the request and report the customer to your sponsor
  Acknowledge the request and advise the customer to submit a formal change request
  Convene a meeting of the project team and rewrite the scope statement.
  2. You are managing an internal R&D project. The initial test results are very poor. You are afraid your management might cancel the project, and this could reflect poorly upon you. Verification testing could be done quickly and inexpensively. You should:
  
  Be the first to recommend canceling the project
  Inform management about the results and wait for a response
  Inform management immediately and recommend retesting for verification
  Withhold the information from management until you perform additional tests to verify the initial results
  3. During an informal meeting with your project client you are offered a substantial monetary incentive to alter the configuration of the product to meet the client's personal need. This change may result in additional project costs and schedule delays. The appropriate action to take would be:
  
  Refrain from accepting the offer and advise the customer to submit a request to the change control board.
  Accept the offer and issue an internal configuration change request to the design group
  Obtain additional information about the request and the customer's personal need before accepting the offer.
  Delay acceptance of the offer until you can ensure that you can protect yourself from any legal liabilities.
  4. As the project manager for a very large and highly visible project you receive a preliminary press release for your approval before distribution. You are expected to approve the release without comment. Your review identifies a major discrepancy regarding some key project financial estimates that may mislead the intended recipients. As the project manager it is your responsibility to:
  
  Inform the project sponsor of the discrepancy and refuse to approve the release
  Approve the release but send a memo to the sponsor advising that you are aware of the discrepancy and will refer any questions your receive to the sponsor
  Completely rewrite the press release and include the correct information
  Approve the release as requested
  Your project is running out of cash and significant work remains. You are directed by senior management to instruct your people to use another project's charge numbers while working on your project. You should:
  
  Follow instructions
  Inform the corporate auditors
  Understand the background of management's instructions before taking any action
  Shut down the project, if possible
  6. While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects. You should:
  
  Reject the estimate and remove the functional manager from the project
  Request the supporting details for the estimate to ensure it has been properly prepared.
  Accept the estimate and plan to use the additional funding as a reserve.
  Question each functional manager for information about this estimate
  You are working in a country where it is customary to exchange gifts between contractor and customer. Your company code of conduct clearly states that you cannot accept gifts from any client. Failure to accept the gift from this client may result in termination of the contract. The action to take in this case would be:
  
  Provide the customer with a copy of your company code of conduct and refuse the gifts.
  Exchange gifts with the customer and keep the exchange confidential
  Contact your project sponsor and /or your legal or public relations group for assistance.
  Ask the project sponsor or project executive to exchange gifts.
  8. During your assignment as project manager you add a new member to your project team. This new team member was recently hired from a competitor and offers to share a substantial amount of proprietary information from his previous company. This information could put you and your team in a very strong position for future business. You are aware of a non compete clause in the new hire's condition of employment. You should:
  
  Accept the information and agree to keep it confidential between you and the new hire.
  Review the condition of employment with the new hire and advise her to reconsider the offer.
  Review the information and only accept only what may have a direct impact on the project's financial status.
  Ignore the offer to share and move forward with the project
  9. You are asked to write a paper for your sponsor so that he/she can present it at a technical meeting. You are informed that his/her name will be the only name on the paper. You should:
  
  Follow instructions
  
  Follow instructions but demand that your name also appears
  Refuse to follow the instructions
  Go over the head of your sponsor seeking advice
  An example of a conflict of interest would be:
  
  As a public official you make a decision about a contract award that will benefit you personally
  You and a functional manager disagree with a task cost estimate
  Your sponsor decides to cancel your project because it no longer supports the company strategy
  Your personality conflicts with that of a key member of your project team.
  11. Each of the following describes the use of an ethical approach except:
  
  Attempting to understand the religious and cultural sensitivities of the country in which you have been assigned.
  Ensuring that personal interest does not interfere with your decision making process.
  Accepting gifts in exchange for favoring one contractor over another
  Maintaining confidentiality of sensitive information obtained during the project life cycle.
  12. To maintain the customer's schedule, massive overtime will be required between Christmas and New Years. Many of your team members have put in for vacation during this time. You should:
  
  Let the schedule slip and inform the customer
  First give the employees the choice of working overtime
  Make the employees cancel their vacation plans and work overtime
  Hire temporary employees for the overtime
  13. Which of the following situations describes a violation of the PMP?Professional Code of Conduct?
  
  Accepting a gift that is within the customary guidelines of the country or province you are currently working in.
  Use of confidential information to advance your position or influence a critical decision.
  Complying with laws and regulations of the state or province in which project management services are provided
  Disclosing information to a customer about a situation that may have an appearance of impropriety.
  14. In order to balance the needs of the many stakeholders involved in your project the most desirable method to achieve resolution of conflicts would be:
  
  Compromise
  Forcing
  Controlling
  Confrontation
  15. You receive a contract to perform testing for an external client. After contract award, the customer provides you with the test matrix to use for your 16 tests. The vice president for engineering says that the customer's test matrix is wrong, and she will use a different test matrix, which should give better results. This is




 相关文章  热门文章
PMP试题1
PMP试题2
最新PMP考试试题
PMP认证考试试题精选(68)
PMP认证考试试题精选(67)
PMP认证考试试题精选(66)
PMP认证考试试题精选(65)
PMP认证考试试题精选(64)
PMP认证考试试题精选(63)
PMP认证考试试题精选(62)

 文章评论


认证培训
热门专题       more
相关下载
论坛新帖
博 客