  671. The work breakdown structure (WBS) is first developed in which scope management process?
  A. Initiation
  B. Scope planning
  C. Scope change control
  D. Scope Definition
  E. Scope verification
  ANS: D
  
  672. The project charter is prepared in which scope management process?
  A. Initiation
  B. Scope planning
  C. Scope Definition
  D. Scope change control
  E. Scope verification
  ANS: A
  
  673. In which of the following scope management processes is the scope management plan prepared?
  A. Initiation
  B. Scope planning
  C. Scope Definition
  D. Scope change control
  E. Scope verification
  ANS: B
  
  674. Which of the following is not a scope management process?
  A. Initiation
  B. Scope planning
  C. Scope Definition
  D. Scope change control
  E. Scope verification
  ANS: D
  
  675. The initial document that formally recognizes the existence of a project is the _____ .
  A. Scope baseline
  B. Management plan
  C. Project charter
  D. Configuration control report
  E. None of the above
  ANS: C
  
  676. Which of the following are included as part of a scope statement?
  A. Project justification
  B. Project deliverables
  C. Project objectives
  D. All of the above
  E. B and C
  ANS: D
  
  677. Project life cycles are very useful for _____ and _____ .
  A. Configuration management, termination
  B. Objective setting, information gathering
  C. Standardization, control
  D. Configuration management, weekly status updates
  E. Approval, termination
  ANS: C
  
  678. Work packages are used to:
  A. Represent units of work at a level where work is performed.
  B. Clearly distinguish one work package from all others assigned to a single functional group.
  C. Limit the work to be performed to relatively short periods of time.
  D. All of the above.
  E. A and B only
  ANS: D
  
  679. "Hard logic" in the preparation of a network refers to:
  A. Discretionay dependencies
  B. External depenencies
  C. Mandatory dependencies
  D. All of the above
  E. A abd B only
  ANS: C
  
  680. The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
  A. Discretionary
  B. Mandatory
  C. External
  D. Soft logic
  E. Subcontracted
  ANS: B
  
  
  681. Sources for data on activity durations and resource requirements can be gathered from which of the following:
  A. Past project records (historical data)
  B. Commercial techniques (standard practices, rules of thumb)
  C. Past project team members knowledge (experience, oldtimers)
  D. All of the above
  E. A and C only
  ANS: D
  
  682. Which of the following can affect network durations?
  A. Skills of the resource pool
  B. Calendar dates
  C. Constraints
  D. All of the above
  E. A and B only
  ANS: E
  
  683. A completion of a local government study resides on your critical path. This would most likely be referred to as:
  A. Soft logic
  B. Hard logic
  C. An external dependency
  D. A mandatory dependency
  E. A lost cause
  ANS: C
  
  




 相关文章  热门文章
PMP试题1
PMP试题2
PMP考试样题
最新PMP考试试题
PMP认证考试试题精选(67)
PMP认证考试试题精选(66)
PMP认证考试试题精选(65)
PMP认证考试试题精选(64)
PMP认证考试试题精选(63)
PMP认证考试试题精选(62)

 文章评论


认证培训
热门专题       more
相关下载
论坛新帖
博 客