  611. A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high
  performance will follow. The project manager could be defined as a _____ manager.
  A. 1,9
  B. 9,1
  C. 1,1
  D. 9,9
  E. 5,5
  ANS: A
  
  612. Which of the following are included in the Acquisition phase(s) of the project life cycle.
  A. concept and development
  B. development and planning
  C. execution and phase-out
  D. planning and implementation
  E. concept and planning
  ANS: C
  
  613. Budgetary estimates are the output of the _____ phase(s) of the project.
  A. conceptual
  B. development
  C. implementation
  D. finish
  E. All of the above.
  ANS: B
  
  614. The capacity to get an individual or group to perform a given task is described as:
  A. Authority
  B. Power
  C. Influence
  D. Leadership
  E. Motivation
  ANS: E
  
  615. A team that is just forming needs:
  A. An organization chart
  B. Alternatives and choices
  C. Structure and specificity
  D. Orientation and organization
  E. Opportunities for dialogue and conflict resolution
  ANS: C
  
  616. A work breakdown structure:
  A. assures all work is identified.
  B. subdivides the project into manageable segments.
  C. provides the project sponsor with a time-phase task summary.
  D. both A and B.
  E. All of the above.
  ANS: D
  
  617. For effective communication, the message should be oriented to the _____.
  A. Initiator
  B. Receiver
  C. Media
  D. Management style
  E. Corporate culture
  ANS: B
  
  618. The scope statement provides
  A. A basis for future decisions about a project.
  B. A baseline to accomplish verification measures.
  C. A baseline to evaluate potential scope changes.
  D. All of the above
  E. B and C only
  ANS: D
  
  619. A Work Berakdown Structure is most useful for:
  A. Identifying individual tasks for a project.
  B. Scheduling the start of tasks.
  C. Developing a cost estimate.
  D. Determining potential delays.
  E. A and C.
  ANS: E
  
  620. Communication plays a major role in:
  A. Planning
  B. Organizing
  C. Controlling
  D. Directing
  E. All of the above
  ANS: E
  
  




 相关文章  热门文章
PMP试题1
PMP试题2
PMP考试样题
最新PMP考试试题
PMP认证考试试题精选(68)
PMP认证考试试题精选(67)
PMP认证考试试题精选(66)
PMP认证考试试题精选(65)
PMP认证考试试题精选(64)
PMP认证考试试题精选(63)

 文章评论


认证培训
热门专题       more
相关下载
论坛新帖
博 客